Calculator

Block paving calculator

Enter your area's dimensions and instantly see how much block paving you need with waste, pallet counts, sub-base and jointing sand, and kerbs. This is a rough estimate — the app calculates an exact take-off from your area's real shape.

Area dimensions

Advanced settings

Materials needed

Area
20 m²
Paving with waste
21.6 m²2 pallets
Laying course
1.28 t
Sub-base (MOT Type 1)
5.1 t
Kerbs
18 pcs
Estimated price from
£1,240

Are you a paving contractor? Turn this estimate into a finished quote with a PDF and QR payment.

Try for free

How the paving quantity is calculated

The starting point is the area in m² (width × length). Waste for cutting at edges and curves is added on top — typically 5–10 %, 8 % by default. The result is converted into pallets (a standard pallet of 60 mm block paving covers ~10.8 m²). Underneath the paving goes the sub-base build-up: a 4/8 laying course 3–5 cm thick and a MOT Type 1 sub-base layer 15–25 cm thick; tonnage is worked out from layer thickness and material density (sand ~1.6 t/m³, MOT Type 1 ~1.7 t/m³). Kerbs are counted per piece — from the perimeter of the area, rounded up to whole metres. The estimated price "from" is based on a complete price per m² (materials + labour); real UK prices typically range from £45–90/m² depending on the sub-base, area and laying pattern.

How the calculator works out materialFour steps: area from dimensions, adding eight percent waste, converting to packs of 10.8 m² and turning layer volume into tonnes at 1.7 t/m³ for sub-base and 1.6 t/m³ for sand.HOW IT'S CALCULATEDHow the calculator works out material1Areawidth × length,kerb run2Waste+8% for cuts atthe edges3Packsdivided by 10.8 m²,rounded up4Tonnesvolume × 1.7 sub-base,1.6 sandThe same formulas run the calculator and the paid part of the app, so they can't drift apart.
Four steps the calculator does for you

Why an estimate is not a full take-off

This calculator works from a rectangle. A real area rarely is one: a driveway often has a curve, there's a cut-out around a tree, one side runs along the house and the other along a fence that isn't parallel. A rectangle-based estimate is therefore always a starting point for ordering materials, not a basis for a binding quote.

The second difference is the laying pattern. The calculator applies a flat 8 % waste allowance, which works for a stretcher bond. With herringbone laid at 45 degrees and with three-size modular mixes, cutting happens all around the perimeter and actual consumption is higher. An exact figure only comes from tessellating the actual units across the actual shape.

The third thing is kerbs. Here they're calculated from the perimeter, rounded up. In practice, an off-cut from one corner gets used at the start of the next side, so real consumption tends to be lower. That's exactly where you can save — but only if someone keeps track of the off-cuts.

How to sanity-check the estimate

A quick check that catches most typos: multiply the area by the layer thickness in metres and by the density. For 50 m² and a 20 cm sub-base, that's 50 × 0.20 × 1.7, i.e. 17 tonnes of MOT Type 1. If your supplier quotes five tonnes, the thickness is wrong somewhere.

For pallets, remember they're sold whole. Seventeen square metres with waste rounds up to two pallets, even if a third of the second one is left over. That leftover is your reserve for repairs five years down the line, so don't throw it away.

Kerbs here are rounded up from the perimeter to whole metres, which is a safe estimate for ordering. In real installation, the off-cut from one corner gets used at the start of the next side, so actual consumption tends to be a bit lower. That's exactly where larger areas can save money — but only if someone keeps track of the off-cuts.

Frequently asked questions

How many block paving units are there per m²?

It depends on the unit size: 200×100 mm block paving needs about 50 units/m², 100×100 mm block needs about 100 units/m². The calculator works in m², so you don't need to work out the unit count yourself.

How much sub-base and sand do I need under block paving?

A typical build-up is a MOT Type 1 sub-base 15–25 cm thick and a 4/8 laying course of sand 3–5 cm thick. The calculator converts these to tonnes using thickness and density (sand ~1.6 t/m³, MOT Type 1 ~1.7 t/m³).

Why allow for waste when ordering paving?

Cutting at edges and curves means some units are wasted. A typical allowance is 5–10 % (8 % by default). Add more for complex shapes.

Is this calculation accurate?

It's a rough estimate from area and perimeter. For an exact take-off from your area's real shape — with laying pattern, curves, cut-outs and kerbs counted per piece — use the Paving Planner app, and generate a quote straight from it.

Written by Michal Antal, who builds Paving Planner. The numbers in this article come from the same app paving contractors use for their quotes. Last reviewed 29 July 2026.